Juniper Green Energy Subsidiary Juniper Green Stellar Commissions 15.5 MW Wind Capacity - 200 MW FDRE Project Now At 368.95 MWp And 201 MWh BESS

Juniper Green Energy Limited has informed that its wholly owned subsidiary Juniper Green Stellar Private Limited has commissioned 15.5 MW of wind power capacity on October 1, 2026. This is part of its 200 MW Firm and Dispatchable Renewable Energy project and follows an earlier intimation on September 8, 2026.

Visual for representation only

Key Highlights Of The Announcement

Who Is Involved

The parent company is Juniper Green Energy Limited, formerly Juniper Green Energy Private Limited. The project is being executed by its wholly owned subsidiary Juniper Green Stellar Private Limited.

What Has Been Commissioned

15.5 MW of wind power capacity has been commissioned on October 1, 2026. It forms part of the 200 MW Firm and Dispatchable Renewable Energy (FDRE) project.

Where Does The Project Stand Now

With this addition, capacity commissioned under this project now stands at 368.95 MWp and ~201 MWh BESS, out of total planned capacity of 550.6 MWp and ~201 MWh BESS. The overall operational capacity of Juniper Green Energy and its subsidiaries now stands at ~2,740 MWp and ~603 MWh BESS.

Inside The Announcement — Full Details

About The FDRE Project

The 200 MW FDRE project is being developed by Juniper Green Stellar Private Limited. FDRE projects combine solar, wind, and storage to provide firm power. The total planned size for this project is 550.6 MWp of solar and wind capacity along with ~201 MWh of BESS. With 15.5 MW wind added on October 1, 2026, 368.95 MWp and the full ~201 MWh BESS portion are now commissioned.

Project Details

Point Details
Company Juniper Green Energy Limited
Subsidiary Juniper Green Stellar Private Limited, wholly owned subsidiary
Capacity Commissioned 15.5 MW Wind Power
Project 200 MW Firm and Dispatchable Renewable Energy Project
Project Status After Commissioning 368.95 MWp and ~201 MWh BESS commissioned out of planned 550.6 MWp and ~201 MWh BESS
Total Operational Capacity of Group ~2,740 MWp and ~603 MWh BESS
Commissioning Date October 1, 2026
Previous Update September 8, 2026

Conclusion

On October 1, 2026, Juniper Green Energy through its subsidiary Juniper Green Stellar Private Limited commissioned 15.5 MW of wind power capacity under its 200 MW FDRE project. The project now has 368.95 MWp and ~201 MWh BESS commissioned against a planned 550.6 MWp and ~201 MWh BESS. The total operational capacity of Juniper Green Energy and its subsidiaries now stands at ~2,740 MWp and ~603 MWh BESS.